RDA Commercial and Apartment Building Plan Approval in Rawalpindi: Documents and Fees

RDA commercial and apartment building plan approval in Rawalpindi: the 18 item checklist, Rs 20 and Rs 30 per sq ft fees, height charges above 38 feet, 30 days.

Ali Akhtar, author at Pakistan EraAli Akhtar6 min read
A concrete building frame under construction against a clear sky, for RDA commercial and apartment plan approval in Rawalpindi

RDA approves apartment and commercial building plans in Rawalpindi for a scrutiny fee of Rs 20 per square foot for apartments and Rs 30 per square foot for commercial buildings, with extra height charges above 38 feet. The file needs soil, structural and MEP reports, a builder's agreement on Rs 1,200 e-stamp paper and a height NOC, and RDA's timeline is 30 days.

This is a much longer file than a house map. Below is the full RDA checklist, sorted by what you have to collect, what the engineers must sign and what you pay.

RDA's commercial checklist covers three kinds of land

The Rawalpindi Development Authority (RDA) publishes one checklist for apartment and commercial plans in Rawalpindi Improvement Trust (RIT) schemes and the RDA controlled area, and a separate one for RDA approved private housing schemes. The engineering papers are largely the same.

The difference is the ownership proof. In an RIT scheme you bring the allotment, transfer and possession letter issued by RDA, plus an application for verification of ownership and possession from RDA's estate directorate. In the controlled area you bring the attested registry, the original fard malkiyat for map, the original intiqal (mutation) and the original aks shajra, which is the copy of the village field map.

Where the plot isOwnership papers
RIT schemeRDA allotment, transfer and possession letter; ownership verification application; sub-division letter and plan if divided
RDA controlled areaAttested registry; original fard malkiyat for map; original intiqal; original aks shajra
RDA approved private schemeSeparate RDA checklist for private schemes

Before you buy land for a project, check the scheme on the RDA approved and illegal housing scheme lists. A commercial plan inside an illegal scheme has no route to approval.

The engineering file has up to 18 items

Beyond ownership, RDA asks for BR forms, a damages undertaking, stamped plans, structural drawings, a stability certificate, a vetting certificate for multi-storey buildings, MEP drawings, a soil report and a builder's agreement with the engineers.

  1. Owner's CNIC, attested copy.
  2. BR forms 1, 2, 3, 4, 6, 10, 11 and 17, attached to the RDA Building Regulations.
  3. Undertaking for damages (BR-5) on Rs 1,000 e-stamp paper.
  4. Proposed building plans: four ammonia prints, two cloth mounted, stamped by a registered architect and structural engineer.
  5. Structural drawings for a multi-storey building, four sets, stamped by the structural engineer and the vetting engineer.
  6. Structure stability certificate from the structural engineer, registered with RDA.
  7. Vetting certificate for a multi-storey building from an RDA registered vetting engineer.
  8. MEP (mechanical, electrical and plumbing) drawings and certificate, signed by a PEC registered engineer.
  9. Soil investigation report, signed by a PEC registered engineer.
  10. Agreement of the builder with the resident engineer, structural engineer and architect on Rs 1,200 e-stamp paper.
  11. NOC from the Civil Aviation Authority (CAA) or RDA for height clearance.
  12. Traffic Impact Assessment (TIA) and Environmental Impact Assessment (EIA), where they apply.

PEC is the Pakistan Engineering Council, which registers engineers. A vetting engineer is a second, independent engineer who checks the structural design of a tall building.

RDA commercial and apartment building plan file in Rawalpindi: BR forms, structural drawings, vetting, MEP, soil report and height NOC

The two e-stamp papers come from the Punjab e-stamping system. You can check a Punjab e-stamp paper online before the parties sign on it.

Fees: Rs 20 or Rs 30 a square foot, plus height charges

RDA's scrutiny fee is Rs 20 per square foot for apartments and Rs 30 per square foot for commercial buildings. Above 38 feet, extra height charges apply: Rs 100 per square foot for apartments and Rs 60 per square foot for commercial buildings.

ChargeApartmentCommercial
Plan scrutiny feeRs 20 per sq ftRs 30 per sq ft
Extra height charge above 38 feetRs 100 per sq ftRs 60 per sq ft
BR form feeRs 500Rs 500
Damages undertakingRs 1,000 e-stampRs 1,000 e-stamp
Builder's agreementRs 1,200 e-stampRs 1,200 e-stamp

As an example, a commercial plan of 10,000 square feet comes to Rs 300,000 in scrutiny fee at Rs 30 a square foot. The height charge is extra, and only for a building that goes above 38 feet.

RDA scrutiny fee in Rawalpindi: Rs 20 per square foot for apartments, Rs 30 for commercial, height charges above 38 feet

Large plots need a traffic study

RDA says a Traffic Impact Assessment report is required for plots of 4 kanal and above. Buildings that need an environmental review also attach an EIA, and tall buildings need height clearance from CAA or RDA.

Start these early. A traffic study, an environmental approval and an aviation NOC each come from a different office, and the plan file is not complete without them. The 30 day RDA timeline starts from a complete file, not from the first visit.

Six steps from land to an approved commercial plan

Confirm the land is in an RDA area and an approved scheme, hire RDA and PEC registered professionals, prepare the drawings and reports, get the NOCs, file at the One Window Operation Center and pay the fees.

  1. Confirm the land. Check the scheme status and collect the ownership papers for your area.
  2. Hire the team. An architect, structural engineer and vetting engineer from RDA's approved list, and PEC registered engineers for MEP and soil.
  3. Prepare drawings and reports. Plans, structural drawings, stability and vetting certificates, MEP drawings and the soil report.
  4. Get the NOCs. Height clearance from CAA or RDA, a TIA for 4 kanal and above, and an EIA where it applies.
  5. Sign the stamp papers. The BR-5 undertaking and the builder's agreement.
  6. File and pay at the RDA e-Khidmat and One Window Operation Center, on Murree Road near Liaquat Bagh.
Six steps to get a commercial or apartment building plan approved by RDA in Rawalpindi

If a developer is already selling units in a building without an approved plan, buyers can complain about the builder to RDA. Once the building is finished, it also needs a Rescue 1122 building safety certificate if it is 50 feet or taller.

Common questions

What is the RDA fee for a commercial building plan?

RDA's checklist sets the scrutiny fee at Rs 30 per square foot for commercial buildings and Rs 20 per square foot for apartments, plus a Rs 500 BR form fee.

When does RDA charge extra height fees?

Above 38 feet. The extra charge is Rs 100 per square foot for apartments and Rs 60 per square foot for commercial buildings.

Do I need a traffic study for an RDA commercial plan?

Yes, for plots of 4 kanal and above. RDA's sheet says a Traffic Impact Assessment report is required in that case.

Who must sign the soil and MEP reports?

A Pakistan Engineering Council registered engineer. The structural, stability and vetting papers come from engineers registered with RDA.

How long does RDA take to approve a commercial plan?

RDA's sheet shows a 30 day timeline under its e-Khidmat and One Window Operation Center SOPs, counted from a complete file.

How we verified this

What we checked and where we read it.

Last checked 17 November 2026. The document list, fees, height charges, the 4 kanal traffic study rule and the 30 day timeline come from RDA's "Checklist of the documents required for Approval of Apartments/Commercial Building Plans, fees and timelines in RIT Schemes and RDA Controlled Area", on the RDA Downloads page. The same page lists a separate checklist for apartment and commercial plans in RDA approved private housing schemes. RDA's address is from rda.gop.pk. The sheet's timeline box reads 30 days for "Apartment and Commercial Building Plan". The Urdu version of the same sheet labels its 30 day box as residential plans.

About the author

Ali Akhtar, author at Pakistan Era

Tax, Bills and Technology Writer

Ali Akhtar

Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.

TopicsRDARawalpindiBuilding PlanCommercial PropertyPunjab