Attock Refinery Shuts Its Main 32,400 Barrel Crude Unit in Rawalpindi for 5 to 6 Days From 29 November 2026

Attock Refinery shuts its 32,400 barrel main crude unit for 5 to 6 days from 29 November 2026 for maintenance. Three other units keep supplies running.

Shahid Anwar, author at Pakistan EraShahid Anwar5 min read
Get the next update on this story first on WhatsAppFollow, free
Steel distillation columns and pipework at an oil refinery under a hazy winter sky

Short answer: Attock Refinery Limited (ARL) in Rawalpindi is shutting its main crude distillation unit, which can process 32,400 barrels a day, for 5 to 6 days from Sunday 29 November 2026. The work is urgent maintenance and heat exchanger cleaning. ARL told the Pakistan Stock Exchange (PSX) that its other three crude units and its downstream units will keep running so that product supplies continue.

The unit should be back in service around 4 or 5 December 2026. During the shutdown, the refinery's working distillation capacity falls to 21,000 barrels a day, about 39% of its 53,400 barrel design throughput.

Attock Refinery distillation units by capacity in barrels per day, with the 32,400 barrel main unit shut from 29 November 2026

ARL shuts its 32,400 barrel unit from 29 November 2026

Attock Refinery filed a material information notice with PSX on Friday 27 November 2026. It said the refinery plans to shut its main crude distillation unit, with a capacity of 32,400 barrels per stream day (BPSD), for 5 to 6 days from 29 November. The reason given is urgent plant maintenance and heat exchanger cleaning.

A crude distillation unit is the first stage of a refinery. It heats crude oil and splits it into the parts that become petrol, diesel, jet fuel, kerosene and furnace oil. Heat exchangers move heat between hot and cold streams. When they foul, a unit burns more fuel and runs less smoothly, so they are cleaned during short planned stops.

DetailFrom ARL's notice
UnitMain crude distillation unit
Capacity32,400 barrels per stream day
Shutdown startsSunday 29 November 2026
Expected length5 to 6 days
ReasonUrgent plant maintenance and heat exchanger cleaning
Still runningOther three crude distillation units and downstream units
Filed with PSX27 November 2026, under clause 5.6.1 of the PSX Rule Book

The other three units keep running

ARL has four distillation units. With the main one stopped, three remain in service with a combined 21,000 barrels a day: a 10,000 barrel unit, a 6,000 barrel unit and a 5,000 barrel unit. ARL says they will run along with its downstream units to keep products flowing during the month.

ARL unitCapacity (barrels a day)29 November to about 4 December
HBU-I (main unit)32,400Shut for maintenance
HCU10,000Running
HBU-II6,000Running
Lummus unit5,000Running
Total design throughput53,40021,000 running

The unit names and capacities are from ARL's corporate briefing presentation for 2026, filed with PSX on 29 October 2026. The main unit alone is about 61% of the refinery's design throughput.

What the shutdown means for fuel in the north

ARL is one of the refineries that supply the north of the country. Its main products are diesel, petrol, furnace oil, jet fuel, kerosene and bitumen. Its biggest buyers, by its own figures, are Pakistan State Oil (34%), Attock Petroleum (26%), Wafi Energy (16%) and Parco Gunvor (9%).

Oil marketing companies draw on several refineries and on imports, and they keep stocks at their depots. ARL's notice says the shutdown is planned so that supplies continue. For a driver in Rawalpindi or Islamabad, the practical advice is plain:

  1. Buy fuel as you normally would. A short planned refinery stop is not a reason to fill extra cans.
  2. If one pump is dry, try a pump of a different company before assuming a shortage.
  3. Report a pump that refuses to sell at the notified price to the Oil and Gas Regulatory Authority (OGRA).
  4. Check the notified price before you fill, on the page for today's petrol, diesel and LPG rates.

Pump prices are notified by the government under its pricing formula. A refinery maintenance stop does not change the notified price at the pump.

Attock Refinery's biggest buyers by share of sales: PSO 34%, Attock Petroleum 26%, Wafi Energy 16%, Parco Gunvor 9%

ARL earned Rs 18.6 billion in its last quarter

The shutdown comes after a strong quarter. ARL's profit for July to September 2026 was Rs 18.65 billion, against Rs 1.45 billion a year earlier. Earnings per share were Rs 174.89, up from Rs 13.62. Net sales rose to Rs 143.8 billion from Rs 59.3 billion.

ARL, standalone (Rs million)Jul to Sep 2026Jul to Sep 2025
Gross sales202,64588,165
Net sales143,81659,311
Gross profit29,086931
Profit after tax18,6461,452
Earnings per share (Rs)174.8913.62

The board recommended no dividend with those results. The share closed at Rs 915.46 on Friday 27 November 2026, down 0.92%, according to the PSX data portal. It was still up 33.95% for the year.

How shareholders should read the notice

A 5 to 6 day stop of the main unit means less crude processed in the quarter to December. How much that matters for profit depends on refining margins at the time, which the notice does not cover. Listed companies must tell PSX about events that can affect their share price, which is why this notice was filed.

To follow ARL's filings yourself, open its company page on the PSX data portal and read the Announcements tab. The steps are in the guide to finding company announcements on the PSX data portal. Background on the refinery sector's policy is in the page on oil refining policy changes.

Common questions

When does the Attock Refinery shutdown start?

On Sunday 29 November 2026. ARL expects the main crude distillation unit to stay shut for 5 to 6 days.

Why is Attock Refinery shutting a unit?

For urgent plant maintenance and heat exchanger cleaning, according to ARL's notice to PSX.

Will there be a petrol or diesel shortage in Rawalpindi and Islamabad?

ARL says its other three crude units and downstream units stay in operation to keep product supplies uninterrupted during the month.

How big is the unit being shut?

32,400 barrels a day, about 61% of ARL's 53,400 barrel design throughput.

Does the shutdown change the petrol price?

No. Pump prices are notified by the government under its pricing formula, not by a single refinery.

Where is Attock Refinery?

At Morgah, Rawalpindi. It was commissioned in February 1922.

How we verified this

What we checked and where we read it.

We read Attock Refinery's filings on 29 November 2026 from its PSX company page: the disclosure of material information on the shutdown (ARL/FA/ca/1,500.01/18028, 27 November 2026), the financial results for the quarter ended 30 September 2026 (ARL/FA/ca/1,500.88/17952, 20 October 2026) and the corporate briefing presentation for 2026 (filed 29 October 2026), which gives the unit capacities, products and customer shares. The share price is the portal's close stamped 27 November 2026, 4:49 pm. The running capacity, percentages and expected restart window are our arithmetic from those figures.

Free on WhatsApp

Get the next change first on WhatsApp

Price changes, new rules and deadlines that affect your money, in a few short posts a day.

Follow Pakera on WhatsApp

Other followers cannot see your number.

About the author

Shahid Anwar, author at Pakistan Era

Senior Writer, Public Services and Technology

Shahid Anwar

Shahid joined us in 2024 as an author. He is a senior contributor to Pakistan's leading technology websites. He writes detailed articles, mostly covering his expertise in the latest tech, mobiles, apps, gadgets, and step-by-step guides. His ideology is to help people understand the latest trends and explain complex methods through very easy-to-understand guides.

TopicsAttock RefineryPSXPetrolRawalpindiNews