FESCO New Connection Apply Online: ENC Portal, 8 Documents and the 30-Day Timeline in Punjab (2026)

Apply for a FESCO new connection on the ENC portal or a free form. The 8 documents FESCO asks for, NEPRA's 30-day timeline up to 15 kW and demand notice rules.

Ali Akhtar, author at Pakistan EraAli Akhtar5 min read
A new electricity meter box fixed on the outside wall of a freshly built house in Faisalabad

You can apply for a FESCO electricity connection online on the ENC portal at fesco.enc.com.pk, or on a free paper form from your FESCO sub-division. For a load up to 15 kW, NEPRA's Consumer Service Manual gives the company 30 days in total, counted in four stages, and FESCO's own procedure sheet also adds up to 30 days. The clock for installation runs once you have paid the demand notice.

FESCO, the Faisalabad Electric Supply Company, works through six circles, Faisalabad I, Faisalabad II, Jhang, Sargodha, Mianwali and Toba Tek Singh, as its own published lists show. We read FESCO's e-Services page, its FAQs, its Urdu procedure sheet for new connections and NEPRA's Consumer Service Manual on 6 November 2026. This guide puts them together.

Two ways to apply for a FESCO connection

FESCO lists both routes on its e-Services page under "Electricity New Connection".

RouteWhereWhat FESCO says
Onlinefesco.enc.com.pk, the Electricity New Connection (ENC) system"An Online Portal For The General Public of Pakistan"
Paper formYour FESCO sub-division office, or the Urdu and English form on fesco.com.pkThe form is free; the clerk gives a receipt

FESCO's FAQ says a prospective consumer "can get free of cost an application form from the Sub-Division situated in his area". After you submit it, the clerk issues a receipt. Keep that receipt. It is your proof of the date you applied.

Two ways to apply for a FESCO new connection: the ENC portal or the free sub-division form

Documents FESCO asks for

FESCO's Urdu procedure sheet, titled the method for getting a new connection, change of name and change of load, lists these papers for a normal connection. We have translated them into plain English.

  1. The application form, in three copies.
  2. A copy of the relevant tariff signed by you and two witnesses. Witnesses are not needed for a domestic or commercial single-phase connection.
  3. Proof of ownership, such as a registry, fard, sale deed or allotment letter for a housing colony, with every page attested by an oath commissioner, notary public or grade 17 gazetted officer.
  4. An undertaking, on stamp paper and attested, that no other connection or dues exist at the premises, and that you will pay any dues found later.
  5. If the property has more than one owner, written permission from the other owners on attested stamp paper.
  6. If you are a tenant, the owner's attested permission.
  7. An attested copy of your own CNIC.
  8. Attested CNIC copies of two witnesses. Single-phase applicants do not need these.

Industrial applicants need more: a site plan, a power of attorney where there are several owners, and for a limited company its memorandum and articles, incorporation certificate, directors' details and CNIC copies, Form 29 and a charge creation certificate. FESCO also links a specimen of the owner's affidavit and NOC on its Customer Services page.

NEPRA's general rules on documents are in our guide to new connection documents and the demand notice.

FESCO's 30-day timeline for loads up to 15 kW

NEPRA's Consumer Service Manual, Annexure III, sets the time frame for "Connection Category-1", a load up to 15 kW at 400 volts. That covers almost every home and small shop.

StageDays
Register the application, wiring test report, site survey and check4
Prepare the cost estimate and issue the demand notice6
Work order, store approval, issue of material and the work11
Install the meter9
Total30

FESCO's own Urdu sheet for category one, up to 15 kW, breaks the same job into 12 steps that also add up to 30 days. Its FAQ is shorter. It says the connection "would be installed in One Month", and that if a connection is not feasible, you will be told the reasons.

The manual adds a condition. The DISCO must provide the connection within the Annexure III time "after receipt of full payment". So the days that matter most begin once your demand notice is paid. If FESCO runs late, our page on late connections and NEPRA complaints shows how to escalate.

NEPRA time frame of 30 days for a FESCO connection up to 15 kW, in four stages

The demand notice and what you pay

After the survey, FESCO issues demand notices for the capital cost, also called connection charges, and the security deposit. NEPRA's manual gives you 30 days to pay a demand notice. You can ask for a further 30 days of grace, but you must ask at least three days before the first deadline.

Two more rules from the manual can save money:

  • No escalation charge, meaning a later rise in material prices, can be charged to residential consumers up to 20 kW or commercial consumers up to 15 kW.
  • You may ask to pay the demand notice in instalments, with no mark-up.

FESCO publishes a "New Connection Cost Estimates Calculator (for Material)" on its e-Services page. It lists items such as poles, conductors and distribution transformers. FESCO also posts SOPs for consumers who buy material privately for a new connection or a load extension. We did not run a cost estimate, so we give no rupee figure here. For one company's published charges, see our page on IESCO new connection charges.

Track the application and avoid the common delays

Most delays come from missing papers or an unpaid notice. A short checklist:

  • Keep your receipt or ENC tracking number from the day you apply.
  • Get the wiring test report from a licensed contractor before the survey.
  • Have every ownership page attested, not only the first.
  • Pay the demand notice early and keep the bank receipt.
  • If nothing happens, call 118 or your sub-division.

FESCO office numbers are on our pages for the FESCO complaint number and FESCO SDO and XEN mobiles. If you are moving a connection into your own name instead, read our guide to changing the name on an electricity bill.

Common questions

How do I apply for a FESCO new connection online?

Use FESCO's Electricity New Connection portal at fesco.enc.com.pk, which FESCO links from its e-Services page.

Is the FESCO new connection form free?

Yes. FESCO's FAQ says the application form is free of cost from your sub-division.

How long does a FESCO new connection take?

For a load up to 15 kW, NEPRA's manual sets 30 days in total. FESCO's FAQ says one month.

How long do I have to pay the FESCO demand notice?

Thirty days, with a further 30 days of grace if you ask at least three days before the deadline.

Do I need witnesses for a single-phase connection?

No. FESCO's procedure sheet says witness signatures and witness CNICs are not needed for a single-phase connection.

Can FESCO charge more if material prices rise?

Not for residential connections up to 20 kW or commercial ones up to 15 kW, under NEPRA's manual.

What we checked and sources

We read FESCO's e-Services page, FAQs, the Urdu new connection procedure sheet, the ENC portal home page, and NEPRA's Consumer Service Manual, on 6 November 2026. We did not submit an application on the ENC portal or run the cost calculator.

About the author

Ali Akhtar, author at Pakistan Era

Tax, Bills and Technology Writer

Ali Akhtar

Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.

TopicsFESCONew ConnectionElectricityFaisalabadGuides