MEPCO Shutdown Schedule 16 to 30 November 2026: 75 Feeders in Multan, Sahiwal, Bahawalnagar, Vehari and DG Khan

MEPCO shutdown schedule for 16 to 30 November 2026: 75 feeder entries in Multan, Sahiwal, Bahawalnagar, Vehari and DG Khan, with dates and times by feeder.

Ali Akhtar, author at Pakistan EraAli Akhtar6 min read
یہ صفحہ اردو میں پڑھیں
MEPCO shutdown letter dated 13 November 2026 listing feeders, dates and timings from 16 to 30 November

Short answer: MEPCO has approved planned power shutdowns on 75 feeder entries between 16 and 30 November 2026, in Multan, Khanewal, Muzaffargarh, Bahawalpur, Sahiwal, Bahawalnagar, Vehari and Dera Ghazi Khan circles. Most cuts last four to five hours in the morning, starting between 7:30 am and 9:00 am. On Monday, 16 November alone, 31 feeders are off, including one in Lodhran.

The Multan Electric Power Company (MEPCO) issued the list in letter No. 3842-60, dated 13 November 2026, from the office of its Chief Executive. A second letter of the same date, No. 3871-81, adds the Colony feeder in Lodhran from 16 to 18 November. Both are on MEPCO's electricity shutdown page. This list runs alongside the MEPCO shutdowns for 8 to 17 November we covered earlier.

First page of MEPCO shutdown letter 3842-60 dated 13 November 2026 listing feeders, dates and timings
Image: MEPCO shutdown letter, mepco.com.pk, 13 November 2026

MEPCO lists 75 shutdown entries from 16 to 30 November

The letter has 75 rows. Each row gives the division, sub division, grid station, 11 kV feeder name, feeder code, the dates and the timings. Some feeders appear twice, with a different set of dates on each row.

Area (circle)EntriesGrid stations
Multan (Mumtazabad, Makhdoom Rasheed, SR Alam)23132 kV Makhdoom Rasheed, 132 kV Qasimpur
Bahawalnagar (Mandi Sadiq Ganj, Haroonabad, Chishtian, Fort Abbas)18132 kV McLeod Ganj, Haroonabad, Chishtian, Fort Abbas, Khichi Wala; 66 kV Chishtian, Buxan Khan
Sahiwal9132 kV Sahiwal-New
Vehari6220 kV Vehari, 132 kV Vehari
Khanewal (Jahanian, Mian Channu)5132 kV Makhdoom Rasheed, 132 kV Mian Channu
Bahawalpur5132 kV Bahawalpur
Dera Ghazi Khan (Taunsa, Jampur)5132 kV Taunsa, 132 kV Jampur
Muzaffargarh (Khan Garh, Kot Addu)4132 kV M/Khas (as printed), 132 kV Gujrat, 66 kV Rang Pur
Total75
Bar chart of MEPCO shutdown entries from 16 to 30 November 2026 by area

The letter says the work is for road widening along the Makhdoom Rasheed road at 11 Kassi, the Bindra Pully, Kacha Pacca Noor Shah, Tounsa, Lodhran to Multan, Sahoo Vehari and Dehli Multan roads, and in Vehari city. Other jobs are re-conductoring the 11 kV Habib feeder, splitting the Mandi Sadiq Ganj and Mian Channu Bazar feeders, and a new transformer at Basti Jamadar, Ghazi Ghat and Basti Ari Kamil.

31 MEPCO feeders are off on Monday, 16 November

The first day is the busiest. These are the feeders whose date list includes 16 November.

AreaFeeders off on 16 NovemberTime
Bahawalpur (132 kV Bahawalpur)Al-Rehman, Bindra Pully, Badar-ud-Din, Industrial Estate, Shahdra8:00 am to 12:30 pm
Lodhran (132 kV Lodhran)Colony8:30 am to 12:30 pm
Multan (132 kV Qasimpur)Old Lar, Pir Ismail, Nishat Mill, A&B, Kareem Abad, Family Food, RPT8:00 am to 1:00 pm
Vehari (220 kV and 132 kV Vehari)Faisal Town, Taimoor Shaheed, Madina Colony, MES Thingi, Bilal, District Jail8:30 am to 1:30 pm
Mian ChannuCity-I, City-III, Hammad Banglow8:00 am to 12:00 noon
JampurKhan Pur, Basti Fouja, Indus, Bukhara8:00 am to 1:00 pm
TaunsaJatt Wala8:00 am to 1:00 pm
Muzaffargarh and Khan GarhMubaraz Shaheed (KD Qureshi), Habib (Rohillan Wali)9:00 am to 1:00 pm, Habib 8:00 am to 1:00 pm
Haroonabad and ChishtianMubarak Abad, Buxan Khan 2nd9:00 am to 2:00 pm, Buxan Khan 8:00 am to 1:00 pm
MEPCO letter 3871-81 approving a shutdown of the Colony feeder on the 132 kV Lodhran grid from 16 to 18 November 2026
Image: MEPCO shutdown letter 3871-81, mepco.com.pk, 13 November 2026

Dates and times by feeder for the rest of November

Many feeders are off on several days, not just one. Find your feeder name below and note every date listed for it.

  • Makhdoom Rasheed grid, Multan: Pir Fakhar Ali, Makhdoom Rasheed, Quaid-e-Azam and Mumtaz Oil Mill on 17, 18, 19, 26 and 28 November, 8:30 am to 1:30 pm. Pir Fakhar Ali, Makhdoom Rasheed and Quaid-e-Azam again on 21, 24 and 25 November. Multan Road (Sahu) and 19-Kassi on 17, 18, 19 and 26 November, STM on 17 and 19 November, then Multan Road, 19-Kassi, Khan Pur, Makhdoom Rasheed and Dogar on 21, 24 and 25 November, all 9:00 am to 1:00 pm.
  • Jahanian, Khanewal: Peer Sadiq Shah and Allama Iqbal on 17, 18, 19, 26 and 28 November, 8:30 am to 1:30 pm.
  • Sahiwal-New grid: Ratti Tibbi, Korray Shah, Noor Shah, 65-Yarey Wala, Medhali Sharif, DHQ Teaching Hospital, Chak 85, Shadman and Civil Hospital on 18, 21, 23, 26 and 30 November, 7:30 am to 12:30 pm.
  • Mandi Sadiq Ganj: City MSG, MCD-I, MCD-II, Amrooka, Head Sulemanki and Al Mushtaq on 25 November only, 9:00 am to 1:00 pm.
  • Chishtian: Main Bazar on 18 and 25 November; City 1st, College and Fareed Kot on 17, 19 and 24 November; Satluj and Shouq Elahi on 18 and 25 November; all 8:00 am to 1:00 pm.
  • Fort Abbas and Khichi Wala: Fort on 18 and 19 November; Fazal Shah and City Khichi Wala on 25 November; 8:00 am to 1:00 pm.
  • Kot Addu: Samson Agri Farm on 28 and 30 November, 9:00 am to 2:00 pm.
  • KD Qureshi, Muzaffargarh: Baseera on 21, 22 and 24 November, 9:00 am to 1:00 pm.

Habib feeder (Rohillan Wali), Jatt Wala (Taunsa) and the four Jampur feeders have the longest runs, with 10 or 11 days each spread across the second half of November.

How to check your MEPCO feeder and prepare

Your feeder name and feeder code are printed on your MEPCO bill. The code is the safest match, because names such as Shadman, Khan Pur and City-I repeat in different towns.

  1. Find the feeder name and code on your MEPCO bill.
  2. Open the electricity shutdown page on mepco.com.pk and open the letter "SD-Rre-16.11.26 to 30.11.26".
  3. Match your feeder code and grid station, then write down every date on that row.
  4. Charge phones and UPS batteries the night before, and fill water tanks early.
  5. If power is still off well after the listed time, call MEPCO on 118.

Our guide to checking a MEPCO shutdown by feeder code explains the letters step by step. For daily load shedding hours, see the MEPCO load shedding schedule, and for complaint lines use our MEPCO complaint number page.

Common questions

Is there a MEPCO shutdown on 16 November 2026?

Yes. 31 feeders are off on 16 November, in Bahawalpur, Lodhran, Multan, Vehari, Mian Channu, Jampur, Taunsa, Muzaffargarh, Haroonabad and Chishtian.

How long is each shutdown?

Most run four to five hours. Sahiwal feeders are off from 7:30 am to 12:30 pm, Bahawalpur from 8:00 am to 12:30 pm, and most Multan and Vehari feeders until 1:00 pm or 1:30 pm.

Why is MEPCO cutting power for so many days?

The letter lists road widening on several main roads, re-conductoring of the Habib feeder, splitting of two feeders and a new transformer. Each job has its own dates, so one feeder can be off on several separate days.

Are hospitals on the list?

Yes. DHQ Teaching Hospital and Civil Hospital feeders in Sahiwal are off on 18, 21, 23, 26 and 30 November from 7:30 am to 12:30 pm. Hospitals normally run on backup power during planned work.

Can the dates change?

Yes. MEPCO's page says the shutdown schedule can change for technical or operational reasons. Check the page again the evening before your date.

Will I get less load shedding on a shutdown day?

The letter asks grid staff to follow a revised load shedding schedule and refers to a compensation schedule. It does not list hours by feeder, so check your feeder on the load shedding page.

How we verified this

What we checked and where we read it.

Checked on 14 November 2026, about 03:40 PKT, on the MEPCO electricity shutdown page. Sources: MEPCO letter No. 3842-60 dated 13 November 2026 (file "SD-Rre-16.11.26 to 30.11.26", three scanned pages) and letter No. 3871-81 dated 13 November 2026 (file "SD-Rre-b.pur-131126", Lodhran). Counts by area and the 16 November total are our own count from the letters. The safety supervisors named on the letters are MEPCO staff and are not listed here.

About the author

Ali Akhtar, author at Pakistan Era

Tax, Bills and Technology Writer

Ali Akhtar

Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.