SBCA Completion Certificate in Karachi: Documents, Fee and the 15 Day Rule
SBCA completion certificate in Karachi: the 15 day rule for Category I houses, seven documents, final inspection, the per sq ft fee and how to track your file.

SBCA issues a completion certificate for a Category I building in Karachi within 15 days, once the owner files a "Notice for Completion and Permission for Occupation" through a licensed professional. The file needs the approved construction permit with plan, CNIC, photos and six sets of the building plan. SBCA inspects the building first, and charges the scrutiny fee for completion plans by the FBR valuation category of the area.
Category I covers most family houses: a bungalow on a plot of up to 399 square yards with up to ground plus two floors. If your house fits that, this is your route.
Category I buildings get a 15 day completion certificate
The Sindh Building Control Authority (SBCA) set a 15 day limit for Category I completion certificates in a January 2020 amendment to the Karachi Building and Town Planning Regulations 2002. The clock runs once every requirement in the regulations is met.
A completion certificate is SBCA's confirmation that a building was built as per its approved plan and may be occupied. SBCA's own procedure calls the application a "Notice for Completion and Permission for Occupation", which is why many people call the result an occupancy certificate.
| SBCA category | What it covers |
|---|---|
| Category I | Bungalow on a plot up to 399 sq yd with up to G+2 floors; any other building on a plot up to 120 sq yd and up to 33 ft high; a non-obnoxious warehouse up to 35 ft high or on a plot up to 1,100 sq yd |
| Category II | All other bungalows; other buildings up to 20,000 sq ft of floor area or 50 ft high |
| Category III | Buildings above 20,000 sq ft or above 50 ft |
| Category IV | Public use, large industrial and public sale buildings |
The 15 day timeline in this notification applies to Category I. Larger buildings go through SBCA's regular approval process under the same regulations.

Seven documents for an SBCA completion file
SBCA asks for the completion notice, the approved construction permit with plan, CNIC or NICOP and photos of the applicants, six sets of plans, and, if ownership changed, the land agency's forwarding letter and the latest ownership document. A licensed professional signs and stamps every document.
- Notice for Completion and Permission for Occupation.
- Approved construction permit with plan.
- CNIC or NICOP of the applicant or applicants: the owner, owners or registered attorney.
- Recent passport size photo of each applicant.
- Forwarding letter from the land owning agency, such as KDA, KMC or the society, if ownership has changed since the plan was approved.
- Last ownership document, if ownership has changed.
- Six sets of the building plan showing elevation, sections and site plan.
Every document must be signed and stamped by the licensed professional, meaning the SBCA licensed architect or engineer who handles your file. Before you hire one, check that the architect or engineer holds an SBCA licence.

Three steps after the house is built
SBCA's six step Category I procedure ends with three completion steps: file the completion notice through the licensed professional, receive SBCA's final inspection, then receive the completion certificate. SBCA lists one day each for the first two and 15 days for the last.
| Step | What happens | SBCA time |
|---|---|---|
| Apply for completion certificate | Owner files the completion notice through the licensed professional (third party) certificate, at the Automated Single Window Facility | 1 day |
| Final inspection | SBCA zone inspects the building against the approved plan | 1 day |
| Completion certificate | Issued once the regulations are met | 15 days |
The first three steps of the same procedure come before construction: a letter from the land owning agency, the building permit from the Single Window Facility, and the first site inspection. If your plan was never approved, start with SBCA building plan approval instead.

The scrutiny fee depends on your area's FBR category
SBCA's fee schedule charges the same per square foot scrutiny fee for proposed building plans and for completion or regularisation plans. For homes it is Rs 16.50 or Rs 12 per square foot, depending on the area's category in the FBR property valuation table.
| Building type | FBR valuation category | Rate per sq ft |
|---|---|---|
| Residential | I, A-I, II, III, IX and X | Rs 16.50 |
| Residential | IV, V, VI, VII and VIII | Rs 12.00 |
| Commercial or public sale | I, IA, II, III, IX and X | Rs 22.00 |
| Commercial or public sale | IV, V, VI, VII and VIII | Rs 17.50 |
| Industrial | All | Rs 20.00 |
| Amenity | All | Rs 12.00 |
These rates come from SBCA's 2023 amendment to Schedule 3-A of the regulations. Your architect will know which FBR category your area is in, and SBCA links the Karachi valuation list from its website.
Track the file and check the certificate
SBCA sends an SMS to the owner or licensed professional at every stage, and the file can be tracked on SBCA's E-Tracking page with its proposal number. SBCA permits carry a QR code that shows the record when scanned.
Keep the acknowledgement receipt. It carries the QR code and the proposal number you need for tracking. If the 15 days pass with no answer, ask your licensed professional to follow up with the zone first. You can also log a complaint against SBCA through the Karachi 1339 portal.
Buyers should ask for the completion certificate as well as the approved plan. For flats, the SBCA approval and NOC for sale of the project is the first check, and utility companies may also ask for building papers: SSGC, for example, has its own rules for a gas connection in an apartment building.
Common questions
How long does SBCA take to issue a completion certificate?
For a Category I building, SBCA's regulations say the completion certificate is issued within 15 days once all requirements are met. Final inspection is listed as one day.
What is a Category I building in SBCA rules?
A bungalow on a plot up to 399 square yards with up to G+2 floors, any other building on up to 120 square yards and 33 feet, or a small non-obnoxious warehouse.
Who files the SBCA completion notice?
The owner files it through the licensed professional, who signs and stamps every document. SBCA calls it the Notice for Completion and Permission for Occupation.
What is the SBCA completion plan fee?
For residential buildings, Rs 16.50 or Rs 12 per square foot, depending on the FBR valuation category of the area. Commercial buildings pay Rs 22 or Rs 17.50.
Do I need new ownership papers if I bought the house after approval?
Yes. If ownership changed, attach the forwarding letter from the land owning agency and the last ownership document to the completion file.
How we verified this
What we checked and where we read it.
Last checked 17 November 2026. The 15 day rule and document list come from SBCA's notification of 24 January 2020, "Approval of Completion Plan for Cat-I Buildings", and the completion steps from its notification of 27 January 2020 on six procedures and timelines, both linked from the SBCA Timelines page. Building categories are from SBCA's "Categories of Development Works", and the fee rates from the Karachi Building and Town Planning Regulations (Amendment) 2023 in SBCA's "Fees Notification". Tracking and QR code details are from the SBCA FAQ. SBCA's fees file opens with unrelated Sindh Gazette pages before the SBCA notification on page 50 of the gazette.
About the author

Tax, Bills and Technology Writer
Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.