HESCO Net Metering 2026 in Sindh: Apply Online, the Documents and HESCO's Feeder Capacity Sheet for 445 Feeders
HESCO net metering in 2026: apply online on PITC's portal, the documents, the 5 kW minimum load, and HESCO's feeder-wise solar capacity sheet for 445 feeders.

HESCO net metering in 2026 is applied for online on PITC's net billing portal (nmp.pitc.com.pk), by you or your certified installer, with HESCO picked from the company list. You need a 3 phase connection with at least 5 kW sanctioned load, a system no bigger than that load, and room on your transformer. HESCO also publishes a feeder-wise sheet of solar capacity for 445 feeders, worth reading before you buy panels.
The Hyderabad Electric Supply Company (HESCO) supplies Hyderabad and the districts of lower Sindh around it. Its net metering page still carries forms and a checklist from the 2015 regime, including a Rs 1,000 per kW pay order to HESCO. For a home system of 25 kW or less, that fee no longer applies under the 2026 rules.
Who can get HESCO net metering in 2026
A HESCO customer with a 3 phase 400 V or 11 kV connection, a sanctioned load of at least 5 kW, and a solar or wind system no bigger than that load. Solar on your transformer, including yours, must stay within 80% of its rating.
| Rule | 2026 position | HESCO's older checklist |
|---|---|---|
| Connection | 3 phase | 3 phase |
| System size | No more than sanctioned load | Up to 1.5 times sanctioned load |
| Fee up to 25 kW | Nil | Rs 1,000 per kW pay order |
| Largest system | 1 MW | 1 MW |
| Where to apply | PITC net billing portal | Net Metering Unit, HESCO Hyderabad |
Size the system to your sanctioned load, not 1.5 times it. If you need more, raise the load first through HESCO's ENC route. The general rules, deadlines and the export rate are set out in the net metering rules for 2026.
Check HESCO's feeder capacity sheet first
HESCO's "Capacity available for Net Metering Feeder wise" sheet lists 445 feeders with the megawatts of solar each can still take. A second sheet names 79 feeders in Category-I, the zero load shedding group, for net metering. Find your feeder on both.
Your feeder code and name are printed on your HESCO bill. Look it up in the capacity sheet. Figures in its "capacity available" column run from about 2 MW down to 0.03 MW, so some feeders have almost no room left for new solar.

The feeder sheet is a wide view. What decides your case is your transformer, which you check free on the PITC portal with the "Check Transformer Overloading" button and your 14 digit reference number. A full feeder is a warning that transformers on it may be full too.
How to apply for HESCO net metering, step by step
The application is online. You or your installer fill in the form on PITC's portal, upload the documents, and HESCO's field office takes it from there. Keep your HESCO bill, CNIC and the installer's details ready before you start.
- Check your sanctioned load and phase on your HESCO bill. If the load is under 5 kW or the meter is single phase, apply to change it through ENC first.
- Make sure the bill is in your name. If not, change the name at your SDO office.
- Choose an installer on PPIB's certified list with Sindh in its area, and sign the customer agreement.
- Run the transformer check on nmp.pitc.com.pk with your planned system size.
- Click "Apply For Net Billing (By Consumer)", choose HESCO, enter your reference number and check eligibility. Or let the installer apply with the installer button.
- Fill in the form, upload the documents and submit. Note the tracking ID.
- HESCO reviews the file, signs the agreement, issues an estimate for the meter and connection, and installs the two-way meter after you pay.

Documents for a HESCO net metering file
Use the 2026 set from the PITC portal: NEPRA Schedules II to V, the Schedule I interconnection agreement, the installer's customer agreement and the inspection certificate. HESCO's own checklist adds an NTN certificate, the installer's certificate and system warranties, so keep those ready too.
- Attested copy of your CNIC. A company adds its CUIN certificate, an authority letter and Form-29.
- Attested copy of the last paid HESCO bill.
- FBR NTN certificate, which HESCO's checklist lists.
- Data sheets for the panels and inverters.
- Single line diagram, and a site plan showing the outside disconnect switch.
- Inspection certificate signed by an engineer of a certified installer.
- Attested copy of the installer's certificate, and copies of the system and component warranties.
HESCO's checklist also asks for a duplicate attested set of every document. The Rs 1,000 per kW pay order on that checklist was the 2015 licence fee. Under S.R.O. 709(I)/2026 it is nil up to 25 kW, and above 25 kW it is paid to NEPRA.
HESCO contacts for net metering
PITC's directory of focal persons names an Assistant Manager for net metering at HESCO, on 0332-8250473. HESCO's net metering work sits with its Office of Planning and Engineering in Hyderabad. Outages and bill problems go to 118, not to the net metering desk.
For other HESCO numbers, use the HESCO complaint number and XEN list. To follow your file, run a net metering application status check with the tracking ID. If HESCO misses the 2026 deadlines, you can take a net metering complaint to NEPRA.

Common questions
Where do I apply for HESCO net metering?
Online on PITC's net billing portal, nmp.pitc.com.pk, choosing HESCO. Your installer can also apply for you there.
Does HESCO still charge Rs 1,000 per kW?
Not for a system of 25 kW or less. That fee is nil under S.R.O. 709(I)/2026. Above 25 kW, Rs 1,000 per kW is paid to NEPRA.
Can I get HESCO net metering on a single phase meter?
No. You need a 3 phase connection and at least 5 kW sanctioned load on the portal form.
How do I know if my feeder has room for solar?
Find your feeder code from your bill in HESCO's feeder-wise capacity sheet, then run the transformer check on the PITC portal.
How big a system can I install with HESCO?
No bigger than your sanctioned load, up to 1 MW. HESCO's older checklist says 1.5 times, which the 2026 rules replaced.
Which installers can work in Hyderabad?
Companies on PPIB's certified list whose area column includes Sindh.
How we verified this
What we checked and where we read it.
Checked on 15 November 2026 on HESCO's net metering page: the checklist and SOP for capacity up to 25 kW, the feeder-wise capacity sheet (445 feeders), the Category-I zero load shedding feeder list (79 feeders), the flow chart and the application queue sheet, which shows "Nil". The page's "Apply for Net Metering" link points to an older outside system; the live application route is PITC's net billing portal, where we read the consumer form and the directory of focal persons. The 2026 size and fee rules come from the NEPRA (Prosumer) Regulations, 2026 and S.R.O. 709(I)/2026 on nepra.org.pk. None of HESCO's sheets carries a date.
About the author

Tax, Bills and Technology Writer
Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.