LESCO Net Metering 2026 in Lahore: Apply Online in 7 Steps, the Documents and LESCO's Net Metering Numbers

LESCO net metering in 2026: apply online on PITC's portal in 7 steps, the documents, the 5 kW minimum load and LESCO's net metering line, 042-99204840.

Ali Akhtar, author at Pakistan EraAli Akhtar5 min read
Solar panels on the flat roofs of red brick houses in Lahore at sunset, for LESCO net metering

LESCO net metering in 2026 is applied for online on PITC's net billing portal (nmp.pitc.com.pk): choose LESCO, enter your 14 digit reference number, and you or your certified installer complete the form. You need a 3 phase connection with at least 5 kW sanctioned load, and a solar system no bigger than that load. For questions, LESCO's net metering line is 042-99204840.

The Lahore Electric Supply Company (LESCO) serves Lahore, Kasur, Okara, Sheikhupura and Nankana Sahib. It has handled more solar applications than most DISCOs: its own status sheet showed 33,834 applications for 542.3 MW by 31 March 2024. But its net metering page still lists the 2015 regulations and "Schedule 1 to 8" forms, which the 2026 rules replaced.

LESCO net metering rules that apply in 2026

The NEPRA (Prosumer) Regulations, 2026 govern every new LESCO application. Your system can be no bigger than your sanctioned load, solar on your transformer must stay within 80% of its rating, and a system of 25 kW or less pays no NEPRA fee and needs no NEPRA approval.

Rule2026 positionLESCO's older checklist
System sizeNo more than sanctioned loadUp to 1.5 times sanctioned load
Minimum load on the portal5 kWNot stated
Fee up to 25 kWNilLicence forms and fee schedule
Where to applyPITC net billing portalManager (Marketing and Tariff), LESCO HQ
InverterGrid-tied, anti-islandingSingle phase allowed up to 5 kW; 3 phase above

Exported units are bought under net billing at the national average energy purchase price, not at your retail rate. The full rules and deadlines are in the net metering rules for 2026.

LESCO net metering 2026 rules compared with LESCO's older checklist

Before you apply: load, name and transformer

Three checks save weeks. Your bill must show a 3 phase connection with at least 5 kW. The bill must be in your name. And your transformer must have room, which you check free on the PITC portal before paying an installer.

  • Load and phase: read the sanctioned load on your LESCO bill. If it is under 5 kW or single phase, apply for a change of load on ENC first. The fees and deposit are explained in how to extend your electricity load.
  • Name: LESCO's checklist says the applicant's name and the name on the bill must be the same. Fix it first with a name change on the electricity bill.
  • Transformer: on nmp.pitc.com.pk, click "Check Transformer Overloading", enter the reference number and your planned size.
  • Installer: choose a company on PPIB's certified list whose area includes Punjab, and check its validity date.

How to apply for LESCO net metering, step by step

The whole application is online. Once submitted, LESCO's field office reviews it, signs the agreement, sends an estimate for the two-way meter, and installs it after you pay. Each stage has a deadline under the 2026 rules.

  1. Open nmp.pitc.com.pk and click "Apply For Net Billing (By Consumer)". Your installer can use the installer button instead.
  2. Pick "Convert to Net Meter" for an existing connection, enter your 14 digit LESCO reference number, choose LESCO and check eligibility.
  3. Verify the installer: the installer types its portal password.
  4. Enter your details in English, your system size in kW, and the feeder and tariff shown on your bill.
  5. Add your CNIC, email, two mobile numbers and two witnesses' CNICs.
  6. Upload the documents as JPG, JPEG or PDF and submit. Save the tracking ID.
  7. Pay LESCO's estimate when it arrives. The meter should be installed within 15 working days of payment.
Steps to apply for LESCO net metering online in Lahore

Documents for a LESCO net metering file

Use the 2026 forms from the PITC portal: NEPRA Schedules II to V and the Schedule I interconnection agreement. Add your CNIC, your last paid bill, the technical data, a single line diagram, a site plan and the installer's inspection certificate.

DocumentWho provides it
NEPRA Schedules II to V (2026 set)You, filled in and signed
Schedule I interconnection agreementYou and LESCO
Attested CNIC copy and last paid bill in the same nameYou
Data of panels and inverters, single line diagram, site plan with outside disconnect switchInstaller
Inspection certificate and customer agreementCertified installer

Skip LESCO's old Schedules III, IV, VI and VII for a home system of 25 kW or less. Those were the licence papers of the 2015 regime. Above 25 kW, NEPRA's concurrence and a Rs 1,000 per kW fee still apply.

LESCO net metering contacts in Lahore

LESCO's net metering checklist gives 042-99204840 and five mobile numbers for net metering information. Its paper filing address was the Manager (Marketing and Tariff), LESCO Headquarters, 22-A Queens Road, Lahore. Outages still go to 118.

  • Net metering information: 042-99204840, 0320-0520202, 0320-0520203, 0320-0520206, 0320-0520271, 0320-0520282.
  • LESCO focal person for net metering in PITC's directory: an Assistant Director, MIRAD, on 0370-4990173.
  • Faults and outages: 118, or SMS 8118. Other numbers are in the LESCO complaint number list.

Track the file with a net metering application status check. If LESCO misses a deadline, write to the SDO, then file a net metering complaint to NEPRA.

LESCO net metering applications by March 2024

Common questions

How do I apply for LESCO net metering?

Online on PITC's net billing portal, choosing LESCO and entering your reference number. A certified installer can apply for you.

What is LESCO's net metering phone number?

042-99204840, plus five mobiles on LESCO's checklist, including 0320-0520202.

Can I get LESCO net metering on single phase?

No. You need a 3 phase connection with at least 5 kW sanctioned load on the portal form.

How big can my solar system be with LESCO?

No bigger than your sanctioned load, up to 1 MW. LESCO's old 1.5 times rule no longer applies to new applications.

Do I pay LESCO a fee for net metering?

There is no NEPRA fee up to 25 kW. You pay LESCO's estimate for the two-way meter and connection work.

How long does LESCO take to install the net meter?

The 2026 rules allow about 56 working days in total if every step uses its full limit, with installation within 15 working days of payment.

How we verified this

What we checked and where we read it.

Checked on 15 November 2026 on LESCO's net metering page, including its "Checklist for filing net metering applications" (contact numbers, filing address, inverter notes, 1.5 times rule) and its status sheet dated 31 March 2024. LESCO's page still lists the 2015 regulations, Amendments I to IV and "Schedule 1 to 8". On PITC's net billing portal we read the consumer form, the document downloads and the directory of focal persons. The 2026 rules come from the NEPRA (Prosumer) Regulations, 2026 and S.R.O. 709(I)/2026 and S.R.O. 1330(I)/2026 on nepra.org.pk.

About the author

Ali Akhtar, author at Pakistan Era

Tax, Bills and Technology Writer

Ali Akhtar

Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.

TopicsLESCONet MeteringSolarLahorePunjab