RDA House Map Approval in Rawalpindi: Documents, Rs 10 per Sq Ft Fee and 30 Days

RDA house map approval in Rawalpindi: documents for RIT, controlled area and society plots, BR forms, the Rs 10 per sq ft scrutiny fee and the 30 day timeline.

Ali Akhtar, author at Pakistan EraAli Akhtar6 min read
Rolled house plans, a pencil and a ruler on a wooden table, for getting a house map approved by RDA in Rawalpindi

To get a house map approved in Rawalpindi, file the RDA checklist at the RDA e-Khidmat and One Window Operation Center: owner's CNIC, ownership papers, BR forms 1, 3, 4, 6, 10, 11 and 17, a Rs 1,000 damages undertaking and four prints of the plan. The plan scrutiny fee is Rs 10 per square foot, the BR form fee is Rs 500, and RDA's own timeline is 30 days.

The ownership papers change with where the plot sits. A plot in an old Rawalpindi Improvement Trust (RIT) scheme, a plot in the wider RDA controlled area and a plot in an approved private housing scheme each need a different set. The table below sorts that out first, so you do not get sent back from the counter.

RDA approves house plans in three kinds of area

The Rawalpindi Development Authority (RDA) asks for different ownership proof in RIT schemes, in the RDA controlled area and in RDA approved private housing schemes. The building papers, engineer's certificate and fees are the same in all three.

Where your plot isOwnership papers RDA asks for
RIT schemeApplication for verification of ownership and possession from RDA's estate directorate, attested allotment or transfer and possession letter, sub-division letter and plan if the plot was divided
RDA controlled areaAttested registry, original fard malkiyat for map, original intiqal (mutation)
Approved private housing schemeSociety attested allotment or transfer letter, society attested possession letter, original NOC from the society, mortgage release letter if the plot was mortgaged, sub-division letter if RDA divided the plot

Not sure your society is approved? Look it up on the RDA approved and illegal housing scheme lists before you pay an architect. A plot in a scheme on the illegal list will not get a plan through this route.

RDA house map approval in Rawalpindi: ownership papers needed in RIT schemes, the RDA controlled area and approved private housing schemes

The building papers are the same everywhere

Every house plan file needs the owner's attested CNIC, RDA's BR forms, a damages undertaking on stamp paper, four ammonia prints of the plan with two cloth mounted, and a certificate from an RDA registered structural engineer.

  • Owner's CNIC, attested copy.
  • BR forms 1, 3, 4, 6, 10, 11 and 17. These are attached to the RDA Building Regulations. The BR form fee is Rs 500.
  • Undertaking for damages (BR-5) on Rs 1,000 stamp paper. In RIT schemes the sheet says it is stamped by the registered architect and structural engineer.
  • Proposed building plans: four ammonia prints, two of them cloth mounted, stamped by a registered architect.
  • Certificate from a structural engineer registered with RDA.

Buy the Rs 1,000 stamp paper as an e-stamp and keep the challan. You can check that a Punjab e-stamp paper is genuine before you sign the undertaking on it.

RDA publishes a list of approved architects and structural engineers in its Downloads section. Pick your professionals from it. A plan stamped by someone who is not on the list is a common reason for a file to come back.

Fees: Rs 10 a square foot plus Rs 500 for forms

RDA's residential checklist sets the plan scrutiny fee at Rs 10 per square foot and the BR form fee at Rs 500. Add the Rs 1,000 stamp paper for the undertaking and the architect's and engineer's own charges.

ItemAmount on the RDA sheet
Plan scrutiny fee, residentialRs 10 per square foot
BR form feeRs 500
Damages undertaking (BR-5)Rs 1,000 stamp paper
Timeline30 days

Here is a simple example. At Rs 10 a square foot, a plan of 2,000 square feet comes to Rs 20,000 in scrutiny fee. With the Rs 500 form fee and the Rs 1,000 stamp paper, the payments to government come to Rs 21,500 before professional fees.

Apartments and commercial buildings are charged more, at Rs 20 and Rs 30 per square foot, and need a much longer file with soil reports and height clearance. This page covers houses only.

RDA house map approval fees in Rawalpindi: Rs 10 per square foot scrutiny fee, Rs 500 BR form fee, Rs 1,000 stamp paper, 30 days

Six steps from plot papers to an approved map

Collect the ownership papers for your area, hire an RDA listed architect and engineer, fill the BR forms, sign the undertaking, file everything at the One Window Operation Center and pay the scrutiny fee. RDA's stated timeline is 30 days.

  1. Get your ownership papers in order. In the controlled area that means a fresh fard malkiyat for map and the original intiqal. You can get a Punjab fard from an Arazi Record Centre.
  2. Hire an architect and a structural engineer from RDA's approved list.
  3. Prepare the plan. Four ammonia prints, two cloth mounted, stamped by the architect.
  4. Fill BR forms 1, 3, 4, 6, 10, 11 and 17 and sign the BR-5 damages undertaking on Rs 1,000 stamp paper.
  5. File the set at the RDA e-Khidmat and One Window Operation Center and pay the Rs 500 form fee and the scrutiny fee.
  6. Collect the approval when RDA clears the file, within its 30 day timeline.

RDA's head office is on Murree Road near Liaquat Bagh, Rawalpindi. The phone number on its website is 051-5555662.

Six steps to get a house map approved by RDA in Rawalpindi, from ownership papers to collecting the approval

RDA's ready-made house designs save drawing time

RDA's website has a Residential Building Plans Library with sample house designs for common plot sizes: 25 by 50, 30 by 50, 30 by 60, 30 by 70, 35 by 65 and 50 by 90 feet. RDA says they are for reference.

The 25 by 50 size alone has six designs. You can open them, show them to your architect and use one as a starting point. You still file the full checklist, a stamped plan and the engineer's certificate. A sample design is not an approval.

Problems that send a file back, and the fix

Most returns come from missing ownership proof, a professional who is not on RDA's list, or a plot that is not in an approved scheme. Fix the paperwork first, then refile with the same checklist.

  • Old fard or no intiqal. RDA wants the original fard malkiyat for map and the original intiqal in the controlled area. Get a fresh fard and make sure the mutation is sanctioned in your name.
  • Divided plot with no sub-division letter. If the plot was split, attach the sub-division letter and approved sub-division plan.
  • Society plot with a bank loan. Attach the mortgage release letter, or the society NOC will not be enough.
  • Society not approved. If your scheme is on RDA's illegal list, talk to RDA before building. You can also complain about a builder or developer to RDA.

Building on a loan? Banks usually ask for the approved map before they release money, so file early. The plot plus construction home loan process runs in stages tied to the approved plan.

Common questions

How much is the RDA house map fee in Rawalpindi?

RDA's residential checklist sets the plan scrutiny fee at Rs 10 per square foot, plus a Rs 500 BR form fee. The damages undertaking goes on Rs 1,000 stamp paper.

How long does RDA take to approve a house map?

RDA lists 30 days for a residential building plan under the SOPs and timelines of its e-Khidmat and One Window Operation Center.

Which BR forms does RDA need for a house?

BR forms 1, 3, 4, 6, 10, 11 and 17, which are attached to the RDA Building Regulations, plus the BR-5 damages undertaking on stamp paper.

Can I use an RDA sample design instead of hiring an architect?

No. RDA's plans library is for reference. The checklist still asks for plans stamped by a registered architect and a certificate from an RDA registered structural engineer.

What papers do I need for a house map in a private society?

Society attested allotment or transfer letter and possession letter, the society's original NOC, a mortgage release letter if needed, and the sub-division letter if RDA divided the plot.

How we verified this

What we checked and where we read it.

Last checked 17 November 2026. The document lists, fees and the 30 day timeline come from RDA's "Checklist of the documents required for Approval of Residential Building Plans, fees and timelines", listed on the RDA Downloads page. The sample designs are on the RDA Residential Building Plans Library. The checklist is published as an image sheet. It names the fee per square foot but does not say which floor area the rate is applied to, so the 2,000 square foot figure above is an example of the arithmetic.

About the author

Ali Akhtar, author at Pakistan Era

Tax, Bills and Technology Writer

Ali Akhtar

Ali Akhtar is a young and curious voice here at Pakistan Era. He is currently pursuing his A-Levels and has a growing interest in Pakistan’s changing industrial landscape and educational trends. Ali likes to write in a way that helps him explain and explore the world around him. His writing reflects the perspective of the new generation navigating the evolving trends of Pakistan where technology, youth innovation, and shifting opportunities are reshaping the country’s future.