How to Get a DHA Lahore Completion Certificate for Your House

DHA Lahore issues a completion certificate for Rs 7,000 in 21 working days. See the water and sewerage charges, the five steps and why a sale stops without it.

Shahid Anwar, author at Pakistan EraShahid Anwar5 min read
Get last dates and rule changes first on WhatsAppFollow, free
A newly finished cream house front with a wooden door and potted plants in soft evening light

DHA Lahore issues a house completion certificate in 21 working days for Rs 7,000, if its field staff find no violation of the approved plan. Before that you need the permanent water connection (Rs 10,000) and sewerage connection (Rs 5,000). You can apply at the DHA office or on the DHA E-Services Portal at eservices.dhalahore.org.

The completion certificate matters most when you sell or gift the house. DHA Lahore says it will not process the transfer of a house or building, even a hiba to your own children, without one. A duplicate costs Rs 2,000 if the original is lost.

The completion certificate costs Rs 7,000 and takes 21 working days

DHA Lahore's Building Control Branch lists the completion certificate at Rs 7,000 with a timeline of 21 working days, subject to no violation. The certificate is posted to the applicant's address. Late completion and sewer tampering charges are paid separately if they apply.

DHA Lahore serviceTimeCharge
Completion certificate21 working days, if no violationRs 7,000
Permanent water connectionAfter finishing work is doneRs 10,000
Permanent sewerage connectionAfter finishing work is doneRs 5,000
Duplicate completion certificate12 working daysRs 2,000
Duplicate site plan12 working daysRs 2,000
Revised drawing to regularise changes20 working daysRs 4 per sq ft (residential)

A late completion charge applies when the house is not completed and certified within DHA's set period. DHA's building plan approval note says construction should finish within two years. The fine is "as decided by the Authority", so ask the Finance Branch for the current figure.

DHA Lahore completion certificate, water and sewerage connection charges

Get the permanent water and sewerage connections first

DHA connects permanent water and sewerage only after flooring, plastering, gate, doors, windows, wiring and plumbing are ready, and only if the house matches the approved drawing. The completion certificate file then needs the paid water and sewerage challan and DHA's sewer opening letter.

For the connections, DHA's Building Control page asks for:

  • The application form, free at the Customer Care reception.
  • The original and one photocopy of the paid water and sewerage challan.
  • A photocopy of the owner's or attorney's CNIC.
  • Two identical colour photos of the front of the house, 6 by 4 inches, showing the full front including the beam or berm area, driveway and paving. A corner house needs two more of the side.
  • A photocopy of the site plan in the current owner's name.
  • For a 1 kanal or larger house with a solar system of 10 kW or more, a copy of the installer's bill showing purchase and installation date.

After the water line is connected, the construction water pump must be removed under DHA's bye-laws. The sewer is then fully opened.

Apply for the completion certificate in five steps

Write a plain paper application to the Director Building Control, attach photos, two sets of approved drawings and the paid challans, and submit it. DHA's field staff inspect the house. If it matches the approved plan, the certificate is issued and posted to you.

  1. Pay the Rs 7,000 completion certificate fee challan, and any late completion charge, through the Finance Branch or a challan from the E-Services Portal.
  2. Write an application on plain paper to the Director Building Control and fill the Building Completion Performa.
  3. Attach two colour photos of the front, two sets of approved drawings (ammonia prints), the paid challans, the water and sewerage challan, the sewer opening letter and the owner's CNIC copy.
  4. Submit the file at Customer Care or apply online on the DHA E-Services Portal.
  5. Wait for the inspection. If there is no violation the certificate is issued; otherwise DHA sends its observations.
Five steps to get a DHA Lahore completion certificate

Changes from the approved plan must be regularised first

If you built anything different from the approved drawing, DHA advises submitting a revised drawing to regularise it before applying. Otherwise the inspection will record a violation and the certificate will be held back. A residential revision costs Rs 4 per square foot.

Before the inspection, walk the house with your approved drawings in hand. Compare the covered area, the setbacks, any basement and the paving on the road berm, since the photos you submit show the berm and driveway too.

Problem at inspectionWhat to do
Building differs from the approved planSubmit revised drawings and pay the revision fee
Water or sewerage not yet connectedFinish the house, apply for permanent connections, then apply
Completed latePay the late completion charge and attach the challan copy
Sewer tampered with during constructionPay the sewer tampering charge and attach the challan copy
Certificate lostApply for a duplicate with an FIR copy and a newspaper notice, Rs 2,000

Without the certificate, you cannot sell or gift the house

DHA Lahore's Building Control page states that the transfer of a house or building, even on hiba, will not be processed without a completion certificate. The No Demand Certificate for a sale also asks for a copy of it, so a missing certificate stops a sale at the first step.

Buyers should ask for a copy of the completion certificate before paying any token money for a built house. If the seller does not have one, the sale cannot complete until the seller gets it. Lahore houses outside DHA follow the LDA completion certificate process instead, and in Karachi it is the SBCA completion certificate.

A finished house in DHA also pays cantonment tax, and the receipts are needed for a sale. Those can be checked through cantonment board property tax online.

Common questions

How much is the DHA Lahore completion certificate fee?

Rs 7,000, with a timeline of 21 working days if the house has no violation.

Can I apply for the completion certificate online?

Yes. DHA Lahore says the completion certificate can be applied for on its E-Services Portal at eservices.dhalahore.org, which also has a Request Challan option.

Can I sell my DHA house without a completion certificate?

No. DHA Lahore will not process a transfer of a house or building, including a hiba, without one, and the No Demand Certificate asks for a copy.

What does a duplicate completion certificate cost?

Rs 2,000 and 12 working days. You need an application to the Director Building Control, a CNIC copy, the paid challan, a copy of the FIR about the loss and a copy of a newspaper notice.

When will DHA give a permanent water connection?

Only after flooring, plastering, gate, doors, windows, wiring and plumbing are complete and the field staff find the house matches the approved drawing. The water connection fee is Rs 10,000 and sewerage Rs 5,000.

How we verified this

What we checked and where we read it.

We checked DHA Lahore's Building Control services page on 25 November 2026 (completion certificate, new water and sewerage connection, duplicate site plan or completion certificate, and building drawing sections) and opened the DHA Lahore E-Services Portal, whose menu lists Building Control processes, Request Challan and Water Sewerage Bill. The late completion fine is not given as a figure on the page.

Free on WhatsApp

Get last dates and rule changes on WhatsApp

We post new last dates, fee changes and fixes for common problems, a few short posts a day.

Follow Pakera on WhatsApp

Other followers cannot see your number.

Pakera Solves It

Which online process wasted your time this week?

A portal that will not load, a form nobody explains, a complaint that went nowhere. Tell us. Every week we pick one, solve it step by step and publish the answer.

About the author

Shahid Anwar, author at Pakistan Era

Senior Writer, Public Services and Technology

Shahid Anwar

Shahid joined us in 2024 as an author. He is a senior contributor to Pakistan's leading technology websites. He writes detailed articles, mostly covering his expertise in the latest tech, mobiles, apps, gadgets, and step-by-step guides. His ideology is to help people understand the latest trends and explain complex methods through very easy-to-understand guides.

TopicsDHA LahoreCompletion CertificateWater ConnectionLahoreConstruction