QDA Plot NOC, Site Plan and Building Permit in Quetta: The 3 Approvals and Every Document

How to get a QDA plot NOC, site plan and building permit in Quetta: the documents for each stage, the PCATP architect rule and where the map fee is paid.

Shahid Anwar, author at Pakistan EraShahid Anwar6 min read
An empty walled plot with fresh brick foundations and a pile of bricks, brown hills behind, for QDA building approvals in Quetta

To build on a plot in a Quetta Development Authority (QDA) scheme, you need three papers in this order: an NOC from QDA's Estate Directorate, a site plan from the Building Control Section, and then a building permit issued by QDA's Chief Architect. Each stage needs the paper from the stage before it, so skipping ahead only sends your file back.

The steps below are from QDA's own Procedure page, which we read on 15 November 2026. They apply to individual residential or commercial plots in QDA's own housing and commercial schemes.

Three QDA approvals stand between a plot and a building

QDA first confirms you own the plot and have cleared its dues (the NOC). It then marks the plot's boundaries and setbacks on a site plan. Last, it checks your architect's drawings against its building rules and issues the building permit with possession.

StageIssued byYou bring
1. NOC (residential or commercial)Estate Directorate, QDAApplication, CNIC copy, original allotment order, original payment or instalment book
2. Site planBuilding Control Section, QDAApplication to the Chief Architect, CNIC copy, original QDA NOC
3. Building permit and possessionChief Architect, QDAApplication, CNIC copy, original site plan, drawings by a PCATP registered architect, map, security and possession fee
QDA approvals for a plot in Quetta: Estate Directorate NOC, Building Control site plan, Chief Architect building permit

Step 1: get the plot NOC from QDA's Estate Directorate

Apply to the Director Estate with your CNIC, the original allotment order and the original payment or instalment book. QDA issues the NOC only after all dues on the plot are paid, so clear any outstanding instalment first.

  1. Pay any dues still owed on the plot. Your QDA challan can be downloaded from the Challan page on qda.gob.pk by entering your CNIC and plot number.
  2. Write an application to the Director Estate, QDA, asking for a residential or commercial NOC.
  3. Attach a copy of your CNIC and take the original allotment order and the original payment book.
  4. Submit everything at the Estate Directorate.
  5. The directorate checks the papers. If it finds a problem, it tells you; if not, it prepares and issues the NOC.

QDA's table asks for the allotment order and payment book in original, not as copies. Keep your own photocopies before you hand them in. If the allotment order is not in your name because you bought the plot from the first allottee, sort out the transfer with the Estate Directorate before you ask for the NOC.

Step 2: get the site plan from Building Control

Take the NOC to the Building Control desk with an application to the Chief Architect and a copy of your CNIC. The Building Control Section checks the papers and prepares the site plan for your plot.

  1. Write an application to the Chief Architect, QDA, for a site plan.
  2. Attach a copy of your CNIC and the original NOC from the Estate Directorate.
  3. Submit at the Building Control desk.
  4. The section checks the documents. If it raises an observation, you are told; if not, it issues the site plan.
Steps for a QDA site plan in Quetta: application to the Chief Architect, CNIC copy, original NOC, Building Control check

The site plan is the base your architect draws on. Give the architect a copy before any drawing starts, so the design respects the plot lines and setbacks QDA has marked.

Step 3: get the QDA building permit

Apply at the Building Control desk with the NOC, the site plan and detailed drawings signed and stamped by an architect registered with the Pakistan Council of Architects and Town Planners (PCATP). After the design check, you pay the map, security and possession fee at the designated National Bank branch.

  1. Hire an architect registered with PCATP and ask for drawings that follow QDA's building rules.
  2. Submit an application with your CNIC copy, the QDA NOC, the original site plan and the signed drawings.
  3. Building Control checks the documents. If there is an observation, you are told.
  4. If there is none, you submit the layout plan prepared by your architect.
  5. QDA checks the building design against its building rules.
  6. Pay the map, security and possession fee at the designated bank, NBP.
  7. The Chief Architect issues the building permit and hands over possession of the plot.

Possession comes with the building permit, not before it. Do not start digging or bring material on site until both are in your hand.

Do not start building on a QDA plot in Quetta before the building permit: NOC after dues, site plan after NOC, permit after PCATP drawings

Documents to keep ready for every QDA stage

A copy of your CNIC is needed at all three stages. The original allotment order and payment book are needed for the NOC, the original NOC for the site plan, and the original site plan for the building permit. Make copies of each before you submit it.

  • CNIC of the plot owner: copy, every stage.
  • Allotment order: original, for the NOC.
  • Payment or instalment book: original, for the NOC.
  • QDA NOC: original, for the site plan; also listed for the building permit.
  • Site plan: original, for the building permit.
  • Drawings: signed and stamped by a PCATP registered architect.
  • Fee receipt: map, security and possession fee paid at NBP.

QDA's Procedure page does not print the fee amounts. The Building Control Section works them out on your file, so ask for the challan at the desk. For the property tax that follows once the house is built, see property tax in Quetta.

Plots in private Quetta schemes need a different check first

The three steps above are for QDA's own schemes; QDA's Services page says it exercises building control in its own housing and commercial schemes. For a plot in a private scheme, ask the developer which office approves building plans, and first make sure the scheme is on QDA's approved list.

QDA publishes separate lists of approved, illegal and under process private schemes as free PDFs on its website. The wider checks before any purchase are set out in checking a housing scheme before buying a plot. Before buying any plot, also check the registry of the property and the land record of the mauza, as set out under land record in Balochistan.

Common questions

Who issues the NOC for a QDA plot?

The Estate Directorate of QDA, on an application to the Director Estate after all dues on the plot are paid.

What documents do I need for a QDA plot NOC?

An application, a copy of the owner's CNIC, the original allotment order and the original payment or instalment book.

Can I get the site plan before the NOC?

No. The Building Control Section asks for the original NOC from the Estate Directorate with the site plan application.

Does my architect need to be registered?

Yes. QDA asks for drawings signed and stamped by an architect registered with the Pakistan Council of Architects and Town Planners.

Where do I pay the QDA building permit fee?

The map, security and possession fee is paid at the designated National Bank of Pakistan branch, after QDA checks the design.

How do I contact QDA Building Control?

Visit QDA's office at Sariab Link, Quetta, Monday to Friday, 9 am to 4 pm, or call the main lines 081-9211067 and 081-9211076.

How we verified this

What we checked and where we read it.

We read the Quetta Development Authority's Procedure page on 15 November 2026: the sections on the NOC for an individual plot by the Estate Directorate, the site plan by the Building Control Section and the building permit by the Building Control Section, with their document tables. We also read the Challan page (download by CNIC and plot number) and the Contact Us page for the office address, hours and phone lines. The Procedure page gives no fee amounts and no processing days for individual plots. The building permit document table lists the fee as a fourth item without an original or copy mark.

About the author

Shahid Anwar, author at Pakistan Era

Senior Writer, Public Services and Technology

Shahid Anwar

Shahid joined us in 2024 as an author. He is a senior contributor to Pakistan's leading technology websites. He writes detailed articles, mostly covering his expertise in the latest tech, mobiles, apps, gadgets, and step-by-step guides. His ideology is to help people understand the latest trends and explain complex methods through very easy-to-understand guides.

TopicsQDAQuettaBuilding PermitPropertyBalochistan