QDA NOC for a Private Housing Scheme in Quetta: 74 Day Timeline, Documents and the 30% Plot Mortgage
How QDA approves a private housing scheme in Quetta: planning permission in 43 days, NOC in 12, development permit in 19, the documents and the 30% plot rule.

A private housing scheme in Quetta needs three things from the Quetta Development Authority (QDA): planning permission, then a final NOC with an approved layout plan, then a development permit. QDA's own timeline adds up to 74 days: 43 for planning permission, 12 for the NOC and 19 for the mortgage deed and development permit. On top of that, QDA mortgages 30 per cent of the scheme's saleable residential plots until the developer finishes the work.
The steps and timelines below are from QDA's Procedure page, which we read on 15 November 2026. They matter to developers applying, and to buyers who want to know what an approved scheme has been through.
QDA approves a private scheme in three stages
Planning permission confirms the land, the owner and the basic services. The NOC approves the layout plan after a technical check. The development permit follows a mortgage deed and a check of the road, sewerage, water, gas and power drawings.
| Stage | QDA's timeline | Key paper issued |
|---|---|---|
| Planning permission | 43 days | Planning permission letter from Director Town Planning |
| Technical clearance and layout approval | 12 days | Final NOC and approved layout plan |
| Agreements and development permit | 19 days | Mortgage deed, then development permit |
| Total | 74 days | Scheme can start development |

The longest single step in QDA's timeline is the developer's own: 15 days to bring the utility and other certificates. Files that arrive complete move fastest.
Documents QDA asks for at the planning permission stage
The application goes to the Town Planning reception desk with the ownership papers. QDA asks for the land mutation, the sponsor's CNIC, the aks shajra (the revenue map of the land), a location plan, a land use certificate, a non encumbrance certificate and a water availability certificate.
- Mutation of the land in the sponsor's name.
- CNIC of the sponsor or developer.
- Aks shajra of the land.
- Location plan.
- Land use certificate.
- Non encumbrance certificate, showing the land is free of loans and claims.
- Water availability certificate.
After the Director General approves the application, QDA writes to the sponsor for a second set of certificates. These are the registration certificates from the FBR and the Balochistan Revenue Authority, availability certificates from QESCO for electricity, SSGC for gas, WASA for sewerage and sanitation and PTCL for telephone or DSL, an environmental approval from the EPA, and registration from the Social Welfare or Industries Department. The planning permission fee is paid at the designated National Bank branch.
QDA's Private Housing Committee visits the site
Once the certificates are checked, the case goes to QDA's Private Housing Committee, which considers it and visits the site. The Chief Engineer chairs it, with the Director Works and the Director Town Planning as members.
The committee's minutes go to the Director General. After approval, QDA advertises the scheme in the newspaper so the public can object, and the owner pays for the advertisement. Seven days after the advertisement, the Director Town Planning grants planning permission.

The final NOC needs the layout plan and a scrutiny fee
For the NOC, the developer gives QDA four ammonia print sets each of the survey plan, layout plan and location plan, and pays the scrutiny fee at NBP. QDA checks the drawings against its town planning rules, publishes a press release, then issues the NOC and approves the layout.
- Survey plan, 4 sets.
- Layout plan, 4 sets.
- Location plan, 4 sets.
- A general irrevocable power of attorney registered with the Sub Registrar Quetta, if the land is not mutated in the sponsor's name.
- Scrutiny fee receipt from the designated NBP branch.
The power of attorney rule is worth a buyer's attention. It means a scheme can be approved on land the developer holds through a registered power of attorney rather than in its own name, so ask which of the two applies. The land owner's record can be checked through Balochistan's land record.
QDA holds 30 per cent of saleable plots as security
Before development starts, the developer signs a mortgage deed on stamp paper. QDA mortgages 30 per cent of the saleable residential plots to make sure the scheme is developed to the approved layout, and advertises those plots by block, plot number and area.

This protects buyers. A mortgaged plot is held back until the roads, sewerage and other services are built. If you are offered a plot in a newly approved Quetta scheme, ask whether it is one of the mortgaged plots, and check the newspaper notice QDA publishes.
After the mortgage deed, the Engineering Wing checks the services drawings for water supply, electricity, gas and sewerage. The Director General then approves development and the Director Works issues the development permit. The Chief Engineer monitors the work.
Check a scheme's status before you buy
QDA publishes lists of approved, illegal and under process private schemes. A scheme still in any of the three stages above appears on the under process list, which means it has no NOC yet. Only the approved list confirms QDA approval.
Our count of QDA's lists on 15 November 2026 found 51 approved, 139 illegal and 110 under process schemes. The general checks for any scheme are in checking a housing scheme before buying a plot. Stamp duty and registration on your purchase follow the Balochistan land valuation table.
Common questions
How long does QDA take to approve a private housing scheme?
QDA's published timeline is 43 days for planning permission, 12 days for the NOC and layout approval and 19 days for the agreements and development permit, 74 days in all.
How many plots does QDA mortgage in a private scheme?
30 per cent of the saleable residential plots, through a mortgage deed on stamp paper, to secure the development work.
Which utility certificates does QDA ask for?
Electricity from QESCO, gas from SSGC, sewerage and sanitation from WASA and telephone or DSL from PTCL, plus an EPA environmental approval.
Who sits on QDA's Private Housing Committee?
The Chief Engineer as chairman, the Director Works as a member and the Director Town Planning as member and secretary.
Where are QDA fees paid?
The planning permission fee and the scrutiny fee are paid at the designated National Bank of Pakistan branch.
Does QDA have a one window cell for scheme NOCs?
QDA announced a one window operation cell for NOCs of private housing schemes on 2 July 2021, as its news list shows. Ask the Directorate of Town Planning on 081-9211072.
How we verified this
What we checked and where we read it.
We read the Quetta Development Authority's Procedure page on 15 November 2026: the timeline for processing applications for planning permission (11 tasks, total 43 days), the timeline for technical clearance and approval of the plan (5 tasks, 12 days), the timeline for agreements and development activities (8 tasks, 19 days, the monitoring step has no days), and the procedure for planning permission and NOC to private housing schemes, with its document lists, committee members, newspaper notice and 30 per cent mortgage rule. The 74 day total is our sum of QDA's three published totals. The news list on QDA's Downloads page shows the one window cell announcement of 2 July 2021. The page gives no fee amounts.
About the author

Senior Writer, Public Services and Technology
Shahid joined us in 2024 as an author. He is a senior contributor to Pakistan's leading technology websites. He writes detailed articles, mostly covering his expertise in the latest tech, mobiles, apps, gadgets, and step-by-step guides. His ideology is to help people understand the latest trends and explain complex methods through very easy-to-understand guides.